Technical due diligence of a commercial building

How we turned technical, documentation and tenancy risks into decision-ready intelligence before an acquisition.

2026Year
451 m²Lettable area
145 tis. €Short-term CAPEX
THE SITUATION

Before deciding on the acquisition, the investor needed an independent assessment of an older, partly refurbished commercial building. Information about completed upgrades was not enough: their quality, the asset’s remaining service life, document completeness, use compliance and sustainability of tenancy arrangements all required verification.

The client’s identity, exact location and commercially sensitive information have been anonymised.
VERIFIABLE FACTS

From findings to
negotiation evidence.

The facts are drawn from an actual 166-page deliverable. The client, exact address, tenants and contract details are withheld because this was a private acquisition and involved confidential lease information.

YEAR2026

The survey and measurements were completed in June 2026.

TYPE AND SIZERetail and service building

451 m² of identified lettable area.

LOCATIONCentral Slovakia

An older urban asset with partial refurbishments and multiple tenants.

SCOPEBuy-side TDD

Condition, moisture, building services, service life, records, use compliance, tenancy and CAPEX.

FINANCIAL IMPACT€144,994 excl. VAT

Indicative short-term CAPEX for evidenced repairs and renewal, rounded to €145k excluding VAT.

DECISION BENEFITBasis for a counter-offer

CAPEX, missing permits and area discrepancies were structured as evidence for price, conditions or warranties.

INVESTOR QUESTIONS

What needed to be
verified with confidence.

We tailored the audit to the decision the client needed to make, rather than using a generic checklist.

01

Condition and service life

What defects are hidden, which structures and systems are reaching the end of their service life and what requires immediate action?

02

Documents and use

Does the actual condition match the design and permitting documentation, and is the building used for its approved purpose?

03

Tenants and areas

Do contracted areas, spaces actually occupied and declared tenancy arrangements match the conditions observed on site?

04

CAPEX and transaction

What investment must be included in the plan, and which findings should affect price, retention or seller warranties?

OUR APPROACH

From data room to
decision intelligence.

We assessed documents, site conditions and commercial context together so that individual findings formed one coherent technical picture.

01

Data room

Review of designs, permits, inspections, contracts and the available building history.

02

Site survey

Detailed visual inspection of the building fabric, roof, facade, interiors and technical systems.

03

Cross-checking

Comparison of documents, actual conditions, use of premises and information in tenancy arrangements.

04

Risk and CAPEX

Prioritisation of findings, remedial actions, required documents and estimated future investment.

SERVICE LIFE AND DEPRECIATION

Renewals change the
building's technical profile.

The published charts are a basic anonymised example of the data and models used. For confidentiality reasons, we do not publish the extended graphical assessments, including the detailed impact of individual component renewals on the building's overall service life.

01 / SERVICE-LIFE DEVELOPMENT

Building condition over time

The chart shows how renewals of individual components affect the service-life development of a specific property.

Renewed elements
1Electrical installation in 1996
2Heat source, 2005
3Windows and doors, 2016
02 / CALCULATION METHOD

Comparison of depreciation models

We use a total of seven depreciation methods for the professional comparison. For clarity, the chart shows three representative models; at an age of 56 years, the selected semi-quadratic model indicated 50% depreciation.

Click a method name in the legend to hide or show individual curves.

Source: anonymised AUDICO technical due diligence deliverable for a commercial building, 2026. The curves are calculated representations of condition and depreciation and are not a general forecast for another property.

DELIVERABLE PREVIEW

A professional report.
Clear priorities.

The client receives a clear document linking every technical finding to its severity, recommended remediation timeline and financial impact.

  • Executive summary for decision-makers
  • Photographic evidence and findings register
  • Prioritised CAPEX and recommendations
Anonymizovaná titulná strana protokolu technickej due diligence AUDICO bez pozadia
Illustrative anonymised cover based on the actual type of AUDICO deliverable.
KEY FINDINGS

Risks hidden
beyond first impressions.

We did not assess findings in isolation. Each was linked to its effect on safety, operations, compliance or future cost.

BUILDING FABRIC

Moisture and water ingress

Systemic moisture associated with inadequate waterproofing, local roof leakage and water ingress through selected openings and facade areas were identified.

BUILDING SYSTEMS

Declared versus actual scope

The seller stated that the electrical installation had been fully refurbished; however, the site survey confirmed refurbishment on only one floor. Older distribution systems remained elsewhere, the lift was not operational, and valid inspection records were not provided for selected electrical and lightning-protection systems.

DOCUMENTATION

Actual conditions differed from records

Some alterations and uses of space were not adequately supported by the information provided. Other important operational and permitting records were also missing.

TENANCY

Areas and actual use

Cross-checking raised questions about contracted versus occupied areas and the use of selected premises, requiring clarification before the transaction.

AUDICO EXPERT PERSPECTIVE

A defect list alone is not decision intelligence.

In an acquisition, technical condition must be linked to documentation, actual use, tenancy and the timing of future cost. Only then do findings show what must be resolved before signing, what may affect transaction terms and what belongs in the long-term CAPEX plan.

AUDICO expert team · ISEI, s.r.o.
CLIENT DELIVERABLE

Clear intelligence for
the next decision.

The report separated immediate red flags from medium-term repairs and long-term renewal. The client could see what needed resolution before acquisition and what belonged in the investment plan.

  • 01Executive summary and red-flag register
  • 02Prioritised repair plan and indicative CAPEX
  • 03List of missing information and questions for the seller
  • 04Comparison of documents, areas and actual use
  • 05Arguments for price adjustment, retention or seller warranties
The report provided concrete evidence for negotiating price and terms. The final purchase price and transaction outcome are not disclosed for confidentiality reasons.
FREE CONSULTATION

Planning a property